SCOPE AND CONTENTS OF CONSTRUCTION PROJECT
1. The construction project must be developed for the whole quantity of construction envisaged in the design. If a project is constructed in phases, the construction project for the first phase must be devised taking into account the full construction development.

2. The scope of the construction project shall comprise:
a) a construction calendar plan specifying the time frame and priority of the construction of main and auxiliary buildings and structures, process nodes and work stages, start-up or municipal engineering packages with the distribution of investments and quantities of civil and erection works by buildings and structures, and construction stages (Appendix 3, Form 1). The preparatory stage calendar plan shall be drawn up separately to show the distribution of works on a monthly basis; b) general construction arrangement plans for the preparatory and the main construction periods showing the arrangement of permanent buildings and structures, the locations of temporary, including mobile (knock-down) building and structures, permanent and temporary railways and roads and other paths for the transportation of equipment (including heavy-weight and large-sized items), constructions, materials and products; paths for the moving of heavy cranes; utilities, locations for connection of temporary services (utilities) to the existing utilities indicating the sources for supply of the construction site with power, water, heat, and steam; storage yards; main erection cranes and other construction machinery and mechanized plants; existing structures and those to be torn down, locations for beacons fixing the staking out axes of buildings and structures. In cases, when organizational and technical solutions involve the territory beyond the construction site, in addition to the general construction arrangement plan, a construction layout shall be devised as well to show the location of materials supply enterprises and quarries, construction camps, external paths and roads (indicating their lengths and traffic capacity), railway terminals connecting to the Ministry of Railways’ tracks, river and sea jetties, communications and power lines, transportation schemes for the delivery of building materials, constructions, parts and equipment, the boundaries of the facility under construction site and adjacent areas of existing buildings and structures, the areas where woods will be cut and the areas being assigned for the construction needs on a temporary basis; c) organizational process flow charts specifying the optimum sequence of the installation of buildings and structures and indicating the technological sequence of the works; d) a bill of scope of the main civil, erection and special construction works specified in the design and cost estimate documentation, breaking down the works into the main buildings and structures, start-up or municipal engineering packages and construction stages (Appendix 3,
Form 2); e) a schedule of requirement for structures, products, materials and equipment showing the distribution throughout the calendar periods of construction. This schedule shall be drawn up both for the construction project at large and for the main buildings and structures, given the quantities of works and the applicable building material consumption norms (Appendix 3, Form 3*);
f) a time schedule of requirement for major construction machinery and means of transportation for the project at large drawn up on the basis of physical work quantities, freight transportation quantities and rates of work for the construction machinery and means of transportation;
g) a time schedule of requirement for the construction personnel in the main categories;
h) an explanatory note comprising the following information:
the characterization of the construction conditions and complexity;
the substantiation of the construction methods and the possibility of combining the civil, erection and special construction works, including those to be carried out in winter, indicating the time frame for the execution of seasonal works, and the technical solutions for the installation of complex buildings and structures; if necessary, the information on the time frame of execution, the scope of geodetic works and the requirement for material and human resources for their execution must be represented in the documents envisaged in sub-clauses “a”, “c”, “f” and “g” of this clause; the instructions about the methods of the execution of instrumental structure quality control; labor protection activities; a list of the conditions for conservation of the environment; the substantiation of the requirement for basic construction machinery, equipment, means of transportation, power, steam, water, oxygen, acetylene, compressed air as well as for temporary buildings and structures with the solution for a set of mobile (temporary) buildings and structures and the indication of selected standards designs; a list of major construction organizations with the characterization of their production capabilities; the substantiation of the size and outfit of materials, constructions and equipment storage yards as well as the solutions for the moving of heavy-weight oversized equipment and consolidated civil structures; a list of special auxiliary structures, appliances, arrangements and installations as well as complex temporary structures and utilities, the detailed drawings for which must be devised by
design organizations as part of the detailed drawings for the construction project; the requirements, which must be considered in the detailed drawings in connection with the civil structures and equipment installation methods specified in the construction project; the substantiation of the requirement for construction personnel, accommodation and social services to the construction workers;